Please see attached link for information concerning road closures:

June 9, 2021

Project: Washington Ave (Section I) & River Road (Section III) Improvement Project
High Bridge Borough

Please be advised that, on or about June 11, 2021, the reconstruction of the base course pavement on Washington Ave (between Maryland Ave and Wilson Ave) and River Road (between Wilson Ave and Watergate Dr) is scheduled to begin as part of the above referenced project.

This work is expected to take 1 week to complete, weather permitting. The working hours will be from 7 AM to approximately 5 PM. During these hours, the road will be closed to thru traffic but will remain open to residents within the project limits and emergency vehicles.

Due to the nature of this work, driveway and roadway access will be impacted. Our crew will be in verbal contact with affected residents to discuss parking arrangements and the best way to access the roads from day to day. Our crew will also make every effort to make driveways accessible at the end of each workday.

After the installation of the new base course pavement is completed, the surface course paving will follow with a possible short pause in between. Prior to the commencement of the surface course paving, residents will receive an additional notice with further instructions from our office.

If you should have any concerns or questions regarding this project, please feel free to contact our office during the hours of 8:30 a.m. to 5:00 p.m.  (908) 231-7570.

Thank you in advance for your cooperation,

Top Line Construction Corporation